Guelph Transit detours buses during College construction,
starting today



Update — September 1: Construction has ended and buses have resumed their regular route.


The City of Guelph is closing College Avenue East between Victoria Road South and Gordon Street for a project to rebuild the roadway.

Guelph Transit is detouring buses during the project, which likely continues until the end of August.

52 University / Kortright

From Monday, June 15 until Monday, August 31, inbound buses operate along their regular route.

Outbound buses operate along their regular route to Gordon Street and College Avenue, then detour:

southward along Gordon;
eastward along South Ring Road to University Circle,
resuming their regular route around the University Circle.


Guelph Transit is also detouring buses operating on the 52 University Kortright route around construction on Norfolk Street in downtown Guelph.


Inbound buses operate toward downtown Guelph.

Outbound buses operate away from downtown Guelph.