GO extending platforms at Brampton GO Station,
starting April 4



Next week, GO Transit starts another phase of its long-standing project to upgrade Brampton GO Station.

On Monday, April 4, GO contractors start to extend the west end of the north and south platforms at the station. The longer platforms will have more lighting, a public address system and also CCTV (closed-circuit television) coverage for security.

Most of the construction occurs Mondays to Fridays from 8 a.m until 4 p.m. Work continues until the summer.

The longer platforms will allow GO to operate longer trains through the station.