Metrolinx and York Region contractors continue to work on the project to build a rapidway — bus-only lanes in the centre of the roadway.

Here’s what’s going on this week:

  • Cedarland Drive — Contractors are closing the street to traffic until the end of August.
  • intersection of South Town Centre Boulevard with Clegg Road — from 7 a.m. until 5 p.m. each day: Contractors have reduced South Town Centre to just one lane in each direction. They’ve also close east- and westbound curb lanes on Clegg for intersection work. These are long term closures.
  • between Warden Avenue and Highway 404 — from 9:30 a.m. until 3:30 p.m. each day: Contractors are closing multiple lanes. Expect heavy traffic. Work continues until June 6.
  • between Town Centre Boulevard / South Town Centre Boulevard and East Beaver Creek Road / Commerce Valley Drive East — from 9:30 a.m. until 3:30 p.m. each day: Contractors are closing east- and westbound lanes. Expect heavy traffic. Work continues until June 27.
  • between Town Centre Boulevard / South Town Centre Boulevard and Rodick Road — from 9:30 a.m. until 3:30 p.m. each day: Contractors are closing the sidewalks on north and south side of Highway 7. Work continues until June 6.
  • Rodick Road — from 9:30 a.m. until 3:30 p.m. each day: Contractors are closing the southbound and northbound curb lanes north of Highway 7. Work continues until June 6.
  • Fairburn Drive — from 9:30 a.m. until 3:30 p.m. each day: Contractors are closing the north- and southbound curb lanes south of Highway 7. Pedestrians must use the sidewalk on the south side of Highway 7 and cross on the west side of Lunar Crescent to access the Blinds to Go Plaza. Work continues until May 30.
  • between Montgomery Court and Woodbine Avenue — Contractors are restricting westbound traffic to just one lane. Expect very serious delays. Work continues until May 30.
  • Lunar Crescent — Contractors are closing alternating north- or southbound curb lanes north of Highway 7. Work continues until May 30.
  • at Woodbine Avenue — Contractors are closing the southbound curb lane north Highway 7 on Woodbine and the westbound lane on Highway 7 continuously. Work continues until May 30.
  • Woodbine Avenue — Thursday, May 29, from 9:30 a.m. until 3:30 p.m.: Contractors are closing the north- and southbound centre lane north of Highway 7 to remove the median.
  • at Woodbine Avenue — Friday, June 6, from 9:30 a.m. until 3:30 p.m.: Contractors are closing the northbound curb lane on Woodbine and the eastbound curb lane of Highway 7 to install “bike boxes” — safety zones for cyclists.
  • at Frontenac Drive — Contractors are closing westbound curb lanes on Highway 7 and northbound curb lanes on Frontenac continuously to install “bike boxes” — safety zones for cyclists. Work continues until June 6.
  • at Allstate Parkway — Contractors are closing westbound curb lanes on Highway 7 and northbound curb lanes on Allstate continuously to install “bike boxes” — safety zones for cyclists. Work continues until June 6.
  • between East Beaver Creek Road / Commerce Valley Drive East and Chalmers Road — Starting Tuesday, May 19, from 9:30 a.m. until 3:30 p.m. each day: Contractors are closing east- and westbound curb lanes. Work continues until May 30.
  • at West Beaver Creek Road — From 9:30 a.m. until 3:30 p.m. each day: Contractors are intermittently closing westbound curb lanes on Highway 7 and north- and southbound curb lanes on West Beaver Creek to install “bike boxes” — safety zones for cyclists. Work continues until July 14.
  • at Leslie Street — From 9:30 a.m. until 3:30 p.m. each day: Contractors are intermittently closing east- and westbound curb lanes on Highway 7 and north- and southbound curb lanes on Leslie to install “bike boxes” — safety zones for cyclists. Work continues until July 14.
  • at Saddlecreek Drive — From 9:30 a.m. until 3:30 p.m. each day: Contractors are intermittently closing eastbound curb lanes on Highway 7 and north- and southbound curb lanes on Saddlecreek to install “bike boxes” — safety zones for cyclists. Work continues until July 14.

hwy 7 bike box construction.jpg


During Highway 7 rapidway construction, TTC passengers riding buses operating along the 24 Victoria Park, 68 Warden and 224 Victoria Park North routes and York Region Transit passengers riding buses operating along the Viva green, Viva pink, Viva purple, 1 Highway 7, 224B Woodbine and 300 Business express routes should expect detours or delays.