Updated — Thursday, July 7, 1:38 p.m.
Updated — Wednesday, June 1, 2:44 p.m.
Update — Monday, April 25, 5:51 p.m.: The TTC has canceled the closure of Line 3 that it originally scheduled for Saturday, April 30 and Sunday, May 1. It’s also closing Line 2 early Saturday, April 30, instead of closing early Sunday, May 1.
Update — Thursday, March 31, 7:38 a.m.: Since the TTC has revised its schedule for upgrages, we have extensively revised this post.
The TTC has released an official schedule for weekend construction and repairs along three of its four rapid transit lines for 2016. It’s scheduled the first weekend closure for next weekend, Saturday, March 5 and Sunday, March 6.
The TTC says, “Maintaining subway infrastructure in a state-of-good-repair is critical to ensuring a safe, reliable transit system. While the TTC does much of its maintenance work on the subway at the conclusion of service each night, it will continue to require weekend closures to complete improvements to infrastructure and signals, such as automatic train control. One weekend of work during a subway closure equals about five weeks of nightly work.”
Here’s the official list of closures. Note that various events over the year may result in the TTC revising this schedule.
The TTC is closing parts of its rapid transit network every weekend for eight weeks from Saturday, April 2 until Sunday, May 15.
In fact, parts of the rapid transit network are closed (almost) every weekend from Saturday, March 20 until Sunday, December 4, except for these holiday weekends:
- Easter - Friday, March 25 until Monday, March 28;
- Victoria Day - Saturday, May 21 until Monday, May 23;
- Canada Day - Friday, July 1 until Sunday, July 3;
- Simcoe Day - Saturday, July 30 until Monday, August 1.
The TTC is closing parts of its rapid transit network during these holiday weekends:
- Labour Day - Saturday, September 3 until Monday, September 5; and
- Thanksgiving - Saturday, October 8 until Monday, October 10.
More weekends without rapid-transit disruption are:
- Saturday, July
1623and Sunday, July 17; - Saturday, August 20 and Sunday, August 21;
- Saturday, November 12 and Sunday, November 13.
Key dates for commuters (because the TTC has scheduled more than one closure):
- Sunday, April 17 morning, when parts of Lines 1 and 2 are closed;
Sunday, May 1 morning, when part of Line 2 and all of Line 3 are closed.- Sunday, October 9 and Thanksgiving, Monday, October 10, when parts of Lines 1 and 2 are closed; and
Saturday, October 22 and Sunday, October 23, when all of line 3 and part of line 4 are closed.
Line 1 - Yonge - University
- Saturday, March 5 and Sunday, March 6: between Lawrence West and St George - track work.
- Saturday, March 19 and Sunday, March 20: between Lawrence West and St George - track work.
- Saturday, April 16 and Sunday, April 17: between Lawrence West and St George - signal upgrades.
- Saturday, May 28 and Sunday, May 29: between Downsview and St Clair West - signal upgrades.
- Saturday, June 18 and Sunday, June 19: between Downsview and St Clair West - signal upgrades.
- Saturday, July
2316 and Sunday, July2417: between Osgoode and Union - track work. - Saturday, August 6: between St George and Union - track work.
- Saturday, August 27 and Sunday, August 28: between Lawrence and Bloor - track work.
- Saturday, September
2410 and Sunday, September2511: between Downsview and Wilson - track work. - Saturday, September 17 and Sunday, September 18: between Downsview and St Clair West - signal upgrades.
- Saturday, October 8, Sunday, October 9 and Thanksgiving, Monday, October 10: between Downsview and Wilson.
- Saturday, October 15 and Sunday, October 16: between Downsview and St George - signal upgrades.
- Saturday, October 29 and Sunday, October 30: between Downsview and St George - signal upgrades.
- Saturday, November
512 and Sunday, November613: betweenSt. Clair and UnionLawrence and Bloor - track work. - Saturday, November 26 and Sunday, November 27: between Finch and York Mills - track work.
- Saturday, December 3 and Sunday, December 4: between Downsview and Wilson - signal upgrades.
Line 2 - Bloor - Danforth
- Saturday, April 2: between Kennedy and Victoria Park - track work.
- Saturday, April 9 and Sunday, April 10: between Jane and
ChristieBathurst - track work. - Sunday, April 17: between Pape and St George - open late for Prince Edward Viaduct work.
- Saturday, April 23 and Sunday, April 24: between Kennedy and Victoria Park - track work.
Sunday, May 1Saturday, April 30: between Pape and St George - close early for Prince Edward Viaduct work.- Saturday, May 7 and Sunday, May 8: between Jane and Bathurst - track work.
- Sunday, May 15: between Pape and St George - open late for Prince Edward Viaduct work.
- (Updated — Wednesday, June 1.) Saturday, June 4: between Pape and St George - track work.
Saturday, June 11 andSunday, June 12: between Pape and St George - track work.- Sunday, June 26: between Pape and St. George - open late for Prince Edward Viaduct work.
- (Updated — Thursday, July 7, 1:38 p.m.)
Saturday, July 9: between Woodbine and Pape - track work. - (Updated — Thursday, July 7, 1:38 p.m.) Sunday, July 24 between Main Street and Broadview - track work.
- (Updated — Wednesday, June 1.) Sunday, July 24 between Pape and St. George - open late for Prince Edward Viaduct work.
- Saturday, August 13 and Sunday, August 14: between Pape and St George - open late.
- Saturday, September 3, Sunday, September 4 and Labour Day, Monday, September 5: between Pape and St George - bridge work on the Prince Edward Viaduct.
- Saturday, September
1023 and Sunday, September1124: between Pape and St George - bridge work on the Prince Edward Viaduct. - Saturday, October 7, Sunday, October 8 and Thanksgiving, Monday, October 9: between Pape and St George - bridge work on the Prince Edward Viaduct.
- (Updated — Wednesday, June 1.) Saturday, November 5 and Sunday, November 6: between Pape and St George - track work.
Line 3 - Scarborough
Saturday, April 30 and Sunday, May 1: between McCowan and Kennedy - track work.Saturday, June 4 and Sunday, June 5: between McCowan and Kennedy - track work.- Saturday, June 25 and Sunday, June 26: between McCowan and Kennedy - track work.
Saturday, October 22 and Sunday, October 23: between McCowan and Kennedy - track work.Saturday, November 19 and Sunday, November 20: between McCowan and Kennedy - track work.
Line 4 - Sheppard
- Saturday, July 16 and Sunday, July 17: between Bayview and Sheppard - Yonge - track work.
- Saturday, October 22 and Sunday, October 23: between Bayview and Sheppard - Yonge - track work.