TTC installing new PRESTO fare gates
at three more stations, starting July 20



Update — Thursday, September 29, 8:14 p.m.: Construction has ended at Keele Station and passengers are using the new PRESTO-enabled fare gates.


Update — Thursday, September 22, 6:39 p.m.: Construction has ended at Christie Station and passengers are using the new PRESTO-enabled fare gates.


The TTC continues to install new PRESTO fare gates at more stations.

Christie, Glencairn and Keele stations are next.

TTC crews are removing turnstiles and high gates and replacing them with new, PRESTO-enabled fare gates. The new gates provide easier access and improve the flow of passengers into and out of stations.

During construction, you can only access the station at the collector booth aisle at the main entrance.

After the new fare gates are active, you can still use tickets, tokens and Metropasses to pay your fare when you enter the station — but only at the collector booth.

The TTC is assigning ambassadors to the stations to help you figure out how to get around during construction. It will also install way-finding signs.

  • Christie: Construction started Wednesday, July 20. It continues until August 31.
  • Keele: Construction started Friday, July 22. It continues until August 31.
  • Glencairn: Construction starts Tuesday, July 26. It continues until August 31.