Search Transit Toronto

Keele Station construction closes parking,
secondary entrance, February 17 to 19



Update, Sunday, June 18, 6:04 p.m.: The TTC has reopened the facility to store and maintain trains overnight.


TTC continues its project to upgrade Vincent or “Keele” Subway Yard so it can store more subway cars there overnight.

From 2 p.m. Friday, February 17 and from 6 a.m. until 6 p.m. Saturday, February 18 and Sunday, February 19, the TTC is closing its Keele Station parking lot on Indian Road to let crews install electrical cables along the subway bridge. The work also block the eastern secondary entrance into Keele Station off Indian Grove.

Crews use special equipment on a flat-bed truck and portable lighting to complete this work. For safety reasons, they must complete part of this work at night.

You can only enter or exit Keele Station at the main entrance while crews are working.