Update — Friday, *December 15, 4:20 p.m.: Construction has ended.
The TTC is repairing the roof at High Park Station. During this project, the station remains open and the TTC is maintaining regular service along the 2 Bloor - Danforth subway line and the 30 Lambton bus route.
Starting in April, crews have been repairing the roof of the main station structure. Starting Tuesday, September 5, they work on the roof of the Parkview Gardens entrance / exit. During this work, the entrance / exit remains open to passengers.
While crews mostly work during the day, they will occasionally work overnight for safety when
- installing and removing guard rails at the edge of the roof with hand tools at the start and end of the project and
- removing and installing new roof flashings.
The TTC is not using the traditional roofing method applying liquid asphalt from a kettle at this location. Instead, crews are using a three-ply heat application with less odour.
Crews will control dust and debris as much as possible. They’ll place a refuse container in different areas where they’re working, including at the Parkview Gardens entrance / exit.
Crews continue repairing the roof of the Parkview Gardens structure at High Park Station until November 30.