Eglinton Crosstown LRT - Ionview:
Overnight sanitary-sewer installation



Eglinton Crosstown header.jpg

Metrolinx contractors continue building the future Eglinton Crosstown light rail transit line between Mount Dennis and Kennedy.


Starting “as early as” 9 p.m. Wednesday, March 6 until 7 a.m. Thursday, March 7 and continuing nightly, crews are installing a 1.8-metre (six-foot) sanitary-sewer discharge pipe

  • on Eglinton Avenue East, centre lanes, east of Ionview Road.

The work supports construction of the LRT “guideway” — the transit-only lanes in the centre of the roadway, including tracks and passenger amenities — near the future Ionview stop.

At least one lane will be available for traffic in both directions along Eglinton East at all times.

Crews work in three stages during this phase of the work. And they work overnight from 9 p.m. until 7 p.m. “for approximately one (1) week” or until about March 13.


All stages

For transit passengers

  • The TTC may temporarily relocate bus stops near the work zones.
  • Expect delays aboard buses along these routes:
  • 34 Eglinton East; and
  • 334 Eglinton East overnight.

For nearby residents and business people

  • Expect noise in the area from trucks and other construction equipment and dust while crews drill and remove debris.
  • Expect vibration.

Stage 1

For motorists

  • A work zone blocks the centre lanes on Eglinton east of Ionview.
  • Work zones block the north curb and centre lanes on Eglinton west of Ionview.
  • Just one lane is available for through traffic in each direction on Eglinton east and west of Ionview.
  • The eastbound curb lane is also available so you can access business on the south side of Eglinton.
  • The City of Toronto is prohibiting turns in all directions for eastbound traffic on Eglinton at Ionview.
  • The City is also prohibiting left turns into the businesses across from Ionview for westbound traffic.
  • “Paid-duty” Toronto Police Service officers will be on-site to direct traffic.

2019 - 03-06 - Ionview - discharge pipe - stage 1.jpg


Stage 2

For motorists

  • A work zone blocks the centre lanes on Eglinton east and west of Ionview.
  • A work zone blocks the **south curb lane on Eglinton east of Rosemount.
  • Just one lane is available for eastbound through traffic on Eglinton east and west of Ionview.
  • Two lanes are available for westbound through traffic on Eglinton east and west of Ionview.
  • The eastbound curb lane is also available from west of Ionview so you can access business on the south side of Eglinton.
  • The City is prohibiting turns in all directions for eastbound traffic on Eglinton at Ionview.
  • The City is also prohibiting left turns into the businesses across from Ionview for westbound traffic.
  • “Paid-duty” police officers will be on-site to direct traffic.

2019 - 03-06 - Ionview - discharge pipe - stage 2.jpg

Stage 3

For motorists

  • A work zone blocks the centre lanes on Eglinton east and west of Ionview.
  • **A work zone blocks north-south through traffic between Ionview and the business on the south side of Eglinton.
  • Two lanes are available for through traffic in both directions on Eglinton east and west of Ionview.
  • The eastbound curb lane is also available from west of Ionview so you can access business on the south side of Eglinton.
  • The City is prohibiting left turnsfor eastbound traffic on Eglinton onto northbound Ionview.