Metrolinx and York Region opened a rapidway — bus-only lanes in the centre of the roadway — along Highway 7 West, Centre and Bathurst Streets between Dufferin and Yonge Streets, Sunday, January 5.
The Metrolinx / York Region contractors have returned to the rapidway to complete deficiency, warranty and finishing work on the project.
They’re paving the roadway, repairing the storm sewers, planting trees and laying sod on Bathurst and Centre Streets.
Starting Monday, June 29 and from 7 a.m. until 5 p.m. each day, crews repave the main roadway and work zones temporarily block regular traffic lanes. When necessary, regular traffic may detour into the rapidway lanes.
Starting Thursday, July 2 from 7 a.m. until 5 p.m. each day and from 7 p.m. until 5 a.m. overnight, crews repair the red asphalt at these intersections:
- Bathurst Street with New Westminster Drive / Atkinson Avenue;
- Bathurst Street with Worth Avenue / Flamingo Road;
- Centre Street with New Westminster Drive; and
- Centre Street with Dufferin Street.
At a later date, the crews return to repair the intersection of:
- Bathurst Street with Centre Street.
The TTC may temporarily relocate bus stops, while the crews work. TTC passengers aboard buses along this route can also expect delays:
- 160 Bathurst North.
York Region Transit may temporarily relocate bus stops and vivastations, while the crews work. YRT passengers aboard buses along these routes can also expect delays:
- Viva orange;
- 3 Thornhill;
- 23 Thornhill Woods;
- 77 Highway 7; and
- 88 Bathurst.
Red-asphalt repairs and other deficiency, warranty and finishing work on Bathurst and Centre Streets — and the resulting TTC and YRT service changes — continue “for a few weeks” or until about August 1.
The contractor crews work at each intersection in turn, blocking through traffic on the cross streets.
First, from 7 a.m. Thursday, July 2 until 7 p.m. Friday, July 3, they work at the intersection of
- Bathurst Street with New Westminster Drive / Atkinson Avenue,
near the Atkinson vivastation.
The work zone blocks east-west through traffic on New Westminster and Atkinson.
The TTC is detouring buses along this route, while the intersection is closed:
- 160 Bathurst North.

YRT is detouring buses along this route, while the intersection is closed:
- 3 Thornhill.
Deficiency, warranty and finishing work
VivaNext explains,
“When building rapidways for generations to enjoy, it’s important to make sure that the end product meets the requirements we set out to build. That’s why you may see work activity in the first couple of years after infrastructure projects are done.
Deficiencies
“Everything - from the paver stones on the sidewalk, to the glass in the canopies, to the red asphalt - is tested, inspected and verified by qualified engineers with a keen eye for detail. Anything that doesn’t make the grade is placed on a “deficiencies list” that the builder is responsible to remedy.
Warranty work
“Much like when you buy a new house, it can take one or two years for the foundations to settle, and for you to make note of where the finishes are less than desirable. Then the contractor comes back to fix all the nail pops and cracks in the drywall, fill any gaps in the molding and repaint where necessary. It ensures that you are happy with the work, and you get the most out of your home. Warranty work is the same idea for our facilities, stations and rapidways.
“Project managers of infrastructure projects call this the warranty work phase - an opportunity to catch any issues so that they can be fixed while the infrastructure is still under warranty - a period of two years. Note that the two-year warranty period starts when the project is handed over to York Region.
“It often takes all the seasons in a full year to see how things weather in our climate, or perform once in use. You could see operations such as grinding and smoothing of curbs, fixing paint finishes and filling small cracks and, of course, taking note of anything else that needs work. Some upcoming warranty works may be much bigger, like asphalt replacement.
Finishing work
“That’s why this spring on Highway 7 West and along Bathurst and Centre in Vaughan… you’ll see project completion work such as planting trees and shrubs, raised bike lane paving, permanent pavement markings, station finishings like anti-grafitti application, and caulking, etc.
Whether you’re a regular transit rider, or are considering your first trip on the rapidway, know that we are working hard to provide you with a quality experience - and infrastructure that’s built to last.”
Toronto Transit Commission
160 Bathurst North
From 7 a.m. Thursday, July 2 until 7 p.m. Friday, July 3, southbound buses start their trips in Promenade Terminal, then proceed:
east- and southward along Promenade Circle;
eastward along East Promenade; and then
southward along Bathurst Street to Clark Avenue West,
resuming their regular route southward along Bathurst.Southbound buses pick up passengers at a temporary stop
- in the Promenade Terminal at platform 6.
Northbound buses operate along their regular route to Promenade Terminal,
ending their trips at platform 6.
Northbound buses skip their regular stops
- on West Promenade at New Westminster Drive,
- on New Westminster Drive at Highway 7, across from Katerina Avenue, at Beverley Glen Boulevard, across from #1000 New Westminster and at Bathurst Street,
- on Atkinson Avenue at Rosedale Heights Drive [north], east of Dundurn Crescent [north], at Dundurn Crescent [south], beside Rosedale North Park, at Rosedale Heights Drive [south], Centre Street, Campbell Avenue and Rodeo Drive, south of Spring Gate Boulevard and at Clark Avenue West and
- on Clark Avenue West across from York Hill Boulevard.
York Region Transit
3 Thornhill
From 7 a.m. Thursday, July 2 until 7 p.m. Friday, July 3, eastbound buses operate along their regular route to Promenade Terminal, then detour:
eastward along Centre Street to Atkinson Avenue,
resuming their regular route eastward along Centre.Eastbound buses skip their regular stops
- on Centre Street [westbound] at New Westminster Drive,
- on New Westminster Drive at Highway 7, across from Katerina Avenue, at Beverley Glen Boulevard, across from #1000 New Westminster and at Bathurst Street and
- on Atkinson Avenue at Rosedale Heights Drive [north], east of Dundurn Crescent [north], at Dundurn Crescent [south], beside Rosedale North Park and at Rosedale Heights Drive [south] and Centre Street.
Instead, eastbound buses drop off or pick up passengers at temporary stops
- on Centre Street at Bathurst Street and Atkinson Avenue.
Westbound buses reverse the eastbound detour routing.
Westbound buses skip their regular stops
- on Atkinson Avenue at Edmund Seager Drive, across from Rosedale North Park and at Flamingo Road and Bathurst Street and
- on New Westminster Drive west of Bathurst Street and at Beverley Glen Boulevard and Katerina Avenue.
Instead, westbound buses drop off or pick up passengers at temporary stops
- on Centre Street at Bathurst Street and New Westminster Drive.