Metrolinx crews installing "anti-trespass mats" at GO level crossings in Scarborough



Starting Monday, July 13, Metrolinx crews are installing “anti-trespass mats” at several Scarborough level crossings on GO Transit’s Lakeshore East and Stouffville rail corridors. The mats impede pedestrians entering the train right-of-way. The panels surround the tracks and feature a round, cone-shaped pattern on top.

Anti-trespass mats.jpg

Image: Metrolinx

You may notice maintenance crews and machinery in the corridor near each crossing for about a week. Crews mostly work overnight while rail traffic is lightest. You may also hear noise from the machinery and notice some ambient light from each worksite. The crews use back-up beepers, while safely warn workers about trucks and equipment reversing, only during essential work.

Lakeshore East rail corridor
  • Chesterton Shores: Monday, July 13 until about Sunday, July 19;
  • Beechgrove Drive: Monday, July 20 until about Sunday, July 26;
  • Manse Road: Monday, July 20 until about Sunday, July 26;
  • Morningside Avenue: Monday, July 27 until about Sunday, August 2;
  • Poplar Road: Monday, July 27 until about Sunday, August 2;
  • Galloway Road: Monday, August 3 until about Sunday, August 9; and
  • Scarborough Golf Club Road: Monday, August 3 until about Sunday, August 9.
Stouffville rail corridor
  • Huntingwood Drive: Monday, August 10 until about Sunday, August 16;
  • Havendale Road: Monday, August 17 until about Sunday, August 23;
  • Marilyn Avenue: Monday, August 17 until about Sunday, August 23;
  • Corvette Avenue: Monday, August 24 until about Sunday, August 30; and
  • Danforth Avenue: Tuesday, September 8 until about Monday, September 14.