Rutherford GO Station: Temporary bus-loop for GO, YRT buses, starting December 17



09_Alternative_Entry the station_Bdg_day_Updated_Post.jpg

^ Image: Metrolinx

Metrolinx and its contractors continue a long-term project project to transform Rutherford GO Station by 2022, as part of the GO Expansion Program.

Contractors are also building a grade separation — a bridge to carry GO Transit’s Barrie-line tracks over Rutherford Road. This means that motorists will no longer have to wait for a train to pass — improving the safety of everyone near the station. The work zone for the bridge project may change the way you access Rutherford GO Station.


Starting Thursday, December 17, GO Transit is temporarily closing the bus loop on Rutherford Road between Westburne Drive and Peter Rupert Avenue. It’s relocating the loop to the reserved parking lot at #635 Westburne Drive to accommodate crews who are installing a new pedestrian bridge. You can still access the train platform from the temporary bus loop through a an entrance in the reserved parking lot.

GO is detouring buses along these routes to the temporary bus loop:

  • 63 King City / Toronto; and
  • 65F East Gwillimbury / Newmarket / Toronto.

York Region Transit is also detouring buses along these routes:

  • 85 Rutherford;
  • 87 Autumn Hill; and
  • 107B Keele.

Rutherford_GO_Terminal_map_Dec2020.jpg

Construction blocks the permanent bus loop at Rutherford GO Station until December 21.


Since Thursday, June 26, GO Transit has closed about 130 parking spaces in the main parking lot closer to Westburne Drive. You will still have access to parking spaces closer to the station building.

Since Monday, June 29, GO has closed the north half of the platform for construction of a second track and platform.

This temporarily changes how you get on trains until contractors finish this phase of the project “in late 2020” or until about December 31. You may have to adjust where you normally board your train. The doors of some coaches will not open from outside of the train. Spread out along the platform and keep the accessibility coach available for those who need it most.

GO_Rutherford_Sept2020-Phase1 - FULL.jpg

^ Click to enlarge.


Metrolinx has already installed a pedestrian tunnel under the track. Eventually, the tunnel will connect you to the second platform and track that contractors are building as part of this project.


GO has changed how you get into and around the station while contractors build a new parking garage:

  • Traffic on Rutherford Road detours onto a temporary roadway between Westburn Drive and Peter Rupert Avenue. The four-lane detour road will be in place until crews complete the new railway overpass bridge “in spring 2022” or until May 31, 2022.
  • The work zone blocks the south entrance to the station from Westburne Drive. Use the north entrance from Westburne Drive to access the main parking lot.
  • GO has reshaped the passenger drop-off and pick-up area or “Kiss and Ride”. It’s closed the two south lanes and extended the lanes to the west.
  • It’s moved the bike racks to the west side of the station building, close to the Kiss and Ride.
  • It’s relocated all reserved and most carpool parking spaces to a temporary parking lot at 635 Westburne Drive until the parking garage opens in 2022.
  • It’s also relocated motorcycle and scooter parking to the temporary lot.
  • It’s also closed ten regular parking spaces for safety during parking-garage construction.
  • It’s relocated all accessible parking spaces to the two lanes west of the Kiss & Ride.

02_Ariel_Parking_view_S_Post-1553535965463.jpg

^ Image: Metrolinx


Once contractors have finished the project, Rutherford GO Station will include:

  • A new second track and platform to accommodate more frequent Barrie line service in both directions;
  • better platforms with canopies to connect to the new parking garage;
  • new elevators on both platforms to connect to the pedestrian tunnel;
  • the new parking structure with 1,200 more spaces
  • a new railway bridge over Rutherford Road to enhance safety and enable 15-minute two-way electrified GO service in the future;
  • better pedestrian and cyclist connectivity, including a pedestrian bridge over Rutherford Road, and bike lanes on Rutherford Road;
  • 100 new bike parking spots;
  • a better bus loop for better connections to York Region Transit and the passenger drop-off and pick-up area or “Kiss ‘n’ Ride”;
  • a better station building.

rutherford-2.jpg

^ Image: Metrolinx

Metrolinx is also working with the City of Vaughan to improve access into and out of the station, which has become challenging as ridership has grown over the last few years.

Metrolinx expects to open the new parking spots and the grade separation in 2022.

rutherford-3.jpg

^ Image: Metrolinx

You can learn more about the project to improve Rutherford GO Station here and here.


Metrolinx and GO plan to accommodate more passengers and increase service along the Barrie line, as part of their GO Expansion Program (formerly “regional express rail”).


87 Autumn Hill

Thursday, December 17, Friday, December 18 and Monday, December 21, eastbound buses start their trips at stop #1694 on Rutherford Road at Westburne Drive, then proceed:

eastward along Rutherford to the Rutherford GO Station bus-loop access road,
resuming their regular route eastward along Rutherford.

Eastbound** buses skip their regular stop

  • in the bus terminal at Rutherford GO Station.

Instead, eastbound buses pick up passengers at a temporary stop

  • on Rutherford Road at Westburne Drive.

Westbound buses operate along their regular route to Rutherford Road across from the Rutherford GO Station bus-loop access road, then proceed:

westward along Rutherford to stop #1690 on Rutherford at Barrhill Road.

Westbound** buses skip their regular stop

  • in the bus terminal at Rutherford GO Station.

Instead, westbound buses pick up passengers at a temporary stop

  • on Rutherford Road at Barrhill Road.
107B Keele

Thursday, December 17, Friday, December 18 and Monday, December 21, southbound buses start their trips at stop #3868 on Westburne Drive south of Rutherford Road, then proceed:

along their regular route southward along Westburne.

Southbound buses skip their regular stop

  • in the bus terminal at Rutherford GO Station.

Northbound buses operate along their regular route to stop #3867 on Westburne Drive at Rutherford Road,

ending their trips.

Northbound buses skip their regular stop

  • in the bus terminal at Rutherford GO Station.
85 Rutherford

From Thursday, December 17 until Monday, December 21, eastbound buses operate along their regular route to Rutherford Road at the Rutherford GO Station bus-loop access road, then proceed:

along their regular route eastward along Rutherford.

Eastbound** buses skip their regular stop

  • in the bus terminal at Rutherford GO Station.

Westbound buses reverse the eastbound detour routing.

Westbound** buses skip their regular stop

  • in the bus terminal at Rutherford GO Station.