Church Street Weston construction: TTC detour, starting July 22



Starting 7 a.m. Thursday, July 22, the City of Toronto is closing

  • Church Street Weston between Pine Street and Uphill Avenue

to accommodate a project to resurface the roadway.

The TTC is detouring buses along this route, while the street is closed:

59_RR_Jul22.gif

Construction on Church Street and the resulting TTC detour continue until August 30.


59A Maple Leaf via Gary

From 7 a.m. Thursday, July 22 until 7 p.m. Monday, August 30, eastbound buses operate along their regular route to Church and Pine Streets, then detour:

southward along Pine;
eastward along John Street; and then
northward along Jane Street to Maple Leaf Drive,
resuming their regular route eastward along Maple Leaf.

Eastbound buses skip their regular stops

  • on Church Street across from Uphill Avenue and at Jane Street.

Instead, eastbound buses drop off or pick up passengers at a temporary stop

  • on Jane Street at Maple Leaf Drive.

Westbound buses operate along their regular route.

59B Maple Leaf via Church

Eastbound buses operate along their regular route.

From 7 a.m. Thursday, July 22 until 7 p.m. Monday, August 30, westbound buses operate along their regular route to Maple Leaf Drive and Jane Street, then detour:

southward along Jane;
westward along King Street; and then
northward along Pine Street to Church Street,
resuming their regular route westward along Church.

Westbound buses skip their regular stop

  • on Church Street at Pine Street.