Search Transit Toronto

Sweeney Drive Don Mills construction: TTC detour, starting August 23



Starting 7 a.m. Monday, August 23, the City of Toronto is closing

  • Sweeney Drive between Gretna and Penryn Avenues

to accommodate contractors who are upgrading storm and sanitary sewers and inlet control devices as part of the City’s basement flooding=prevention program.

Crews are:

  • excavating the road and digging a trench to access and install the new sewers;
  • replacing City-owned water service pipes that do not meet City standards from the sewer and water mains to private-property lines; and
  • restoring all work areas with asphalt, concrete or grass when they’ve finished working underground.

The TTC is detouring buses along this route, while the street is closed:

  • 91 Woodbine.

91_TFP_Aug23.gif

Construction on Sweeney Drive and the resulting TTC detour continue until August 25.


91C / 91D Woodbine

From 7 a.m. Monday, August 23 until 6 p.m. Wednesday, August 25, southbound buses operate along their regular route to Sweeney Drive and Penryn Avenue, then detour:

southward along Penryn; and then
westward along Woodthorpe Road to Sloane Avenue,
resuming their regular route southward along Sloane.

Southbound buses skip their regular stop

  • on Sloane Avenue beyond Sweeney Drive.

Northbound buses operate along their regular route to Sloane Avenue and Anewen Drive, then detour:

northwestward along Anewen; and then
northward along Gretna Avenue to Sweeney Drive,
resuming their regular route westward along Sweeney.

Northbound buses skip their regular stop

  • on Sweeney Drive across from Sloane Avenue.