Metrolinx and its contractors continue construction of the Hurontario light rail transit line in Mississauga and Brampton.
Since Monday, August 30, the contractors have been relocating utilities
- on Rathburn Road West between west of Duke of York Boulevard and Hurontario Street; and
- on Rathburn Road East just east of Hurontario.
Since Monday, April 11, the work zone has blocked all access by MiWay buses to platform L for the City Centre Terminal — on Rathburn West, just west of the bus exit from the terminal.
MiWay has relocated the stops for buses along these routes:
from platform L to the terminal’s platform A — on Rathburn West, just west of the bus exit from the terminal.
Since Saturday, April 16, it’s relocated the stops for eastbound buses along this route Saturdays, Sundays and holidays from platform L to platform A:
- 26 Burnhamthorpe.
Starting 12:30 a.m. Saturday, April 23, the work zone also blocks platform N for the terminal — on the north side of Rathburn at Station Gate Road. Buses along these routes drop off or pick up passengers at temporary stops in the terminal:
- [20]/archives/weblog/2022/04/22-hurontario.shtml(#ms20w) Rathburn (westbound);
- 26 Burnhamthorpe (westbound); and
- 109 Meadowvale express (northbound).
This phase of LRT construction near the terminal and the resulting MiWay detours continue until April 25 (4 a.m.).
Since Monday, June 21, Brampton Transit has relocated its stop from platform L on the south side of Rathburn West, just west of the bus exit from City Centre Terminal, to platform O on the north side of Rathburn beyond Station Gate Road, affecting service along this route:
- 502 Züm Main.
MiWay
26 Burnhamthorpe
Saturdays, Sundays and holidays, starting Saturday, April 16, eastbound buses operate along their regular route to Rathburn Road West just west of the bus exit from City Centre Terminal, then proceed:
eastward along Rathburn West to platform A — on the south side of Rathburn West, just west of the bus entrance to the terminal.
The buses then proceed along their regular route eastward along Rathburn.
Saturday, April 23 and Sunday, April 24, westbound buses operate along their regular route to Rathburn Road West across from the bus entrance into City Centre Terminal, then proceed:
southward into the terminal, stopping at platform C.
The buses then continue to through the terminal and resume their regular route westward along Rathburn West.
109 Meadowvale express
Starting Monday, April 11, southbound buses operate along their regular route to Rathburn Road West just west of the bus exit from City Centre Terminal, then proceed:
eastward along Rathburn West to platform A — on the south side of Rathburn West, just west of the bus entrance to the terminal.
The buses then proceed along their regular route eastward along Rathburn.
The buses then proceed around the terminal to Rathburn,
resuming their regular route eastward along Rathburn.From 12:30 a.m. Saturday, April 23 until 4 a.m. Monday, April 25, northbound buses operate along their regular route to Rathburn Road West across from the bus entrance into City Centre Terminal, then proceed:
southward into the terminal, stopping at platform C.
The buses then continue to through the terminal and resume their regular route westward along Rathburn West.
20 Rathburn
Starting Monday, April 11, eastbound buses operate along their regular route to Rathburn Road West just west of the bus exit from City Centre Terminal, then proceed:
eastward along Rathburn West to platform A — on the south side of Rathburn West, just west of the bus entrance to the terminal.
The buses then proceed along their regular route eastward along Rathburn.
From 12:30 a.m. Saturday, April 23 until 4 a.m. Monday, April 25, westbound buses operate along their regular route to Rathburn Road West across from the bus entrance into City Centre Terminal, then proceed:
southward into the terminal, stopping at platform B.
The buses then continue to through the terminal and resume their regular route westward along Rathburn West.