Bloor Street West construction affects TTC service, starting July 17



*Update — Monday, August 19, 9:11 a.m.: The City is closing the intersection of Bloor Street West with St. George Street to all traffic, starting Monday, August 19. The TTC is detouring buses.


Update — Monday, July 22, 2024, 7:26 a.m.: The City is closing the westbound lanes between Huron Street and Bedford Road to all traffic, starting Monday, July 22, 2024. The TTC is detouring buses.


Update — Sunday, July 14, 2024, 8:45 a.m.: The City is closing the intersection of Bloor Street West with Spadina Avenue / Spadina Road to all traffic, starting Monday, July 15, 2024. The TTC is detouring buses.


Update — Sunday, July 7, 2024, 12:09 p.m.: The City is closing the intersection of Bloor Street West with Huron Street to all traffic, starting Monday, July 8, 2024. The TTC is detouring buses.


Update — Monday, April 22, 2024, 7:42 a.m.: The City is closing the westbound lanes to all traffic, starting Tuesday, April 23, 2024. The TTC is detouring buses.


Monday, July 17, City of Toronto contractors start a project to rebuild.

  • Bloor Street West, between Spadina Road / Spadina Avenue and Avenue Road / Queen’s Park.

The project involves:

  • replacing the entire road pavement structure, including the asphalt and concrete road base; and
  • repairing road drainage, curbs, boulevards and sidewalks.

Crews are also:

  • installing permanent raised cycle tracks between Spadina and Avenue / Queen’s Park;
  • building a protected intersection at Bloor Street West and St. George Street; and
  • improving green infrastructure and streetscaping.

During the project, the work zone restricts Bloor West to just one lane of traffic in each direction. Passengers aboard buses along this route can expect delays:

  • 300 Bloor - Danforth overnight.

This is the final phase of work that the City has planned along this segment of Bloor Street West after it installed permanent cycle tracks between Bathurst Street and Spadina in 2019 and replaced the water main in August 2021.

Construction on Bloor West (for this year) and the resulting TTC delay continue until December 16.

Support us on Patreon Button

Welcome to Transit Toronto! This is an information site dedicated to public transportation in Toronto, maintained by transit enthusiasts for transit enthuasiasts. This is NOT the official website of the Toronto Transit Commission, Metrolinx or any other transit provider or government agency. To access the official websites of these agencies, consult this page here.