*Update — Monday, August 19, 9:11 a.m.: The City is closing the intersection of Bloor Street West with St. George Street to all traffic, starting Monday, August 19. The TTC is detouring buses.
Update — Monday, July 22, 7:26 a.m.: The City is closing the westbound lanes between Huron Street and Bedford Road to all traffic, starting Monday, July 22, 2024. The TTC is detouring buses.
Update — Sunday, July 14, 8:45 a.m.: The City is closing the intersection of Bloor Street West with Spadina Avenue / Spadina Road to all traffic, starting Monday, July 15, 2024. The TTC is detouring buses.
Update — Sunday, July 7, 12:09 p.m.: The City is closing the intersection of Bloor Street West with Huron Street to all traffic, starting Monday, July 8, 2024. The TTC is detouring buses.
Starting Tuesday, April 23, the City of Toronto is closing
- Bloor Street West, westbound lanes, between Avenue and Spadina roads
to accommodate contractors who are completing a project to rebuild the roadway.
During this phase of the project, contractors are:
- rebuilding the road and cycle track on the north side between Avenue and Bedford roads;
- rebuilding the sidewalk on Bedford, both sides, to 50 meters north of Bloor West;
- rebuilding the intersection of Bloor / Bedford;
- relocating Sidewalks abd utilities, upgrading signals and rebuilding the cycle lane at Bloor / St. George Street;
- rebuilding sidewalks at Bloor / Spadina Avenue / Spadina Road and Bloor / Huron Street; and
- reconnecting the water main between Madison Avenue and Huron Street.
The TTC is detouring buses along this route, while the traffic lanes are closed:
- 300 Bloor - Danforth overnight.
This phase of construction on Bloor Street West and the resulting TTC detour continue until July 8.
Roadway and sidewalk construction on this part of Bloor Street West, affecting TTC service, started Monday, July 17, 2023. It ended for the year in December, 2023.
300A / 300B Bloor - Danforth overnight
Eastbound buses operate along their regular path.
From Wednesday, April 24 until Friday, May 31, westbound buses operate along their regular path to Bloor Street West at Queen’s Park / Avenue Road, then detour:
southward along Queen’s Park and Queen’s Park Crescent West;
westward along Hoskin Avenue and Harbord Street; and then
northward along Spadina Avenue to Bloor West,
resuming their regular path westward along Bloor.Westbound buses skip their regular stops
- on Bloor Street West at Avenue Road, beyond Bedford Road and at St. George Street and Spadina Road.