West Beaver Creek Road Richmond Hill construction: YRT detour, starting February 4



Update — Thursday, April 10, 8:06 a.m.: Construction on West Beaver Creek Road and the resulting YRT detour continue until May 16.


Update — Thursday, February 13, 4:58 p.m.: Construction on West Beaver Creek Road and the resulting YRT detour continue until April 11.


Starting Tuesday, February 4, the City of Richmond Hill is closing

  • West Beaver Creek Road west of Granton Drive

to accommodate crews who are repairing the roadway.

York Region Transit is detouring buses along this route, while the street is closed:

(Updated — Thursday, February 13, 4:58 p.m.) (Updated — Thursday, April 10, 8:06 a.m.) Emergency road repairs and the resulting YRT detour continue until February 14 until April 11 until May 16.


90B Leslie

(Updated — Thursday, February 13, 4:58 p.m.) (Updated — Thursday, April 10, 8:06 a.m.) From Tuesday, February 4 until Friday, February 14until Friday, April 11 Friday, April 16, southbound buses operate along their regular path to Leslie Street and Beaver Creek Road, then detour:

southward along Leslie; and then
westward along West Wilmot Street to West Beaver Creek Road,
resuming their regular path southward along West Beaver Creek.

Southbound buses skip their regular stops

  • on West Beaver Creek Road at Granton Street and beside #63 West Beaver Creek.

Instead, southbound buses drop off or pick up passengers at a temporary stop

  • on Leslie Street at West Wilmot Street.