GO Transit buses replace all UP Express trains due to Metrolinx construction along GO Transit’s 31 Kitchener line this weekend, Saturday, October 31 and Sunday, November 1. UP is also adjusting some late-night service Friday, October 30.

Friday, October 30
- The train that starts its trip in Pearson Airport Terminal 1 to Union Station at 11:39 p.m. is the last eastbound train.
- UP is cancelling the eastbound trains that usually start in Pearson at 11:54 p.m. and 12:09, 12:24, 12:39 and 12:54 a.m.
- The train that starts its trip in Union at 11 p.m. to Pearson is the last westbound train.
- UP is cancelling the westbound trains that usually start in Union at 11:15, 11:30, 11:45 and 11:59 p.m. and 12:15, 12:30, 12:45 and 1 a.m.
Saturday, October 31
Sunday, November 1
- No UP Express trains operate.
- GO buses along temporary route 35 operate express — without stopping — between Pearson Airport Terminal 1 and Union Station Bus Terminal.
- GO replacement buses don’t drop off or pick up passengers at Weston, Mount Dennis or Bloor stations.
- Board TTC buses, streetcars or trains to travel to and from those stations.
Regular service resumes Monday, November 2.
Expect construction for the GO Expansion project along the 31 Kitchener line to disrupt UP Express service during more weekends over the next six months:
- Saturday, November 15 and Sunday, November 16;
- Saturday, December 12 and Sunday, December 13;
- Saturday, February 6 and Sunday, February 7, 2027;
- Saturday, February 27 and Sunday, February 28;
- Saturday, April 17 and Sunday, April 18;
- Saturday, April 24 and Sunday, April 25; and
- Saturday, May 8 and Sunday, May 9.
As we explained, GO is revising service along the 31 Kitchener line due to the construction this weekend.
This weekend, GO is also adjusting service to accommodate Metrolinx construction along three more train lines:
- the 09 Lakeshore East line;
- the 65 Barrie line; and
- the 71 Stouffville line.
After the closure, GO detailed the various activities Metrolinx contractors completed during the weekend:
“During the planned service disruption, crews working on the future Stockyards Station (previously St. Clair-Old Weston Station) decommissioned a railroad utility signal bungalow and removed its associated transformer to allow future track work and platform construction.”
“In addition, essential maintenance was also performed along the line. Crews installed concrete supports at one end of the Grand River Bridge as part of the bridge’s replacement and performed maintenance on crossings.”
“Work was also accomplished within the rail corridor surrounding Union Station, including installing a new crossover - a section of track that allows trains to switch from one track to another.”
“The work involved replacing sections of track, adding new ballast to support and stabilize the tracks, levelling the tracks, testing railway signals and completing safety inspections before returning the tracks to service. This was done using Metrolinx’s new work trains and yellow plant fleet, which are specialized machines that move materials and complete work directly within the rail corridor, limiting road transport.”